Delhi–Mumbai Expressway update: Key DND–Jaitpur-Faridabad link stretch 94% complete; June 2026 deadline se | Delhi News

Date:

Delhi–Mumbai Expressway update: Key DND–Jaitpur-Faridabad link stretch 94% complete; June 2026 deadline se

NEW DELHI: The first leg of the Delhi-Mumbai Expressway’s DND-Jaitpur stretch in Delhi will be ready by June, govt told Lok Sabha on Thursday.In a written reply to a question from south Delhi MP Ramvir Singh Bidhuri, road transport minister Nitin Gadkari said the 59-km DND-Faridabad-Sohna link of the expressway is being developed in three construction packages, out of which the last two packages have been completed and opened for traffic.

Delhi Mumbai Expressway: How does it look?

“Project package-1 from DND junction to Jaitpur of 9 km is in advance stage of construction with physical progress of 94.23% and is scheduled to be completed by June 2026. Package-1 is delayed due to delay in approval of the general arrangement drawings of the structure from the Uttar Pradesh irrigation department for crossing of Agra canal,” Gadkari said.He added that Rs 71,718 crore has been spent till the date on the entire Delhi-Mumbai Expressway project.





Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Advertisementspot_imgspot_img

Popular

More like this
Related

Advertisementspot_imgspot_img